The Old Farmers' Market Field Is About to Become the Bridge Project's Base Camp

"The location of the field office and lay down yard will restrict the Town's use of the Farmer's Market field for numerous years." That sentence comes from Town Manager Haynes Brigman, in a memo prepared for the October 14, 2026 Board of Aldermen meeting. The next sentence explains why the Town was willing to give the field up anyway. The old field at 57 Sea Water Lane was the least damaging place on the island to put the bridge replacement project's trailers, parking and stockpiles.

For anyone who parks near Harbor Way Gardens, walks past the old market grounds, or simply drives Causeway Drive, this is where the three-bridge project first takes up space on land residents use.

What NCDOT Asked For, and What the Town Put on the Table

NCDOT asked to use "the old Farmer's Market field (57 Sea Water Lane)" for a field office and laydown yard for Project HB-0040, the Wrightsville Beach Bridge Replacement Project. The draft memorandum of understanding, dated September 25, 2026, names NCDOT, Balfour Beatty and its subcontractors as the authorized occupants. It covers the replacement of Bridges 21, 22 and 24.

The agreement went before the Board as an item to "consider authorizing," and the published agenda packet describes the proposal, not a final vote. As drafted, the terms are as follows:

Term in the draft MOU What it says
Rent None. Rent-free use "for the duration of construction"
Structures Temporary trailers or modular units only. No permanent structures or modifications
Utilities Arranged and paid for by NCDOT or its contractor
Perimeter Safety fence and silt fence around the staging area
Access points Two construction entrances at locations shown on the site plan
Upkeep Grounds mowed, litter controlled, waste in covered containers, dust controlled in dry weather
Storms Contractor keeps a plan to secure or remove trailers, materials and equipment ahead of a named storm
Public access Public parking and botanical garden access to remain open "at all times"
Exit Property returned to its original condition within 60 days of project completion

The permitted uses are spelled out: temporary field offices for the Department, its inspection team and the contractor, plus employee and visitor parking, material stockpiles and equipment storage. Anything outside the marked staging boundary is off limits, and so is any commercial use unrelated to the project.

Why This Field and Not the Causeway Frontage

The memo gives a short explanation for the choice. NCDOT already holds "a large and extensive right-of-way in front of Town Hall and our multipurpose fields along Causeway Drive" that it could have used for staging. Putting a field office and laydown yard there "would have created significant negative impacts to the Town," which made the old market field "the most practical location compared to alternative locations."

That is the real trade. The memo describes the Causeway Drive right-of-way as land NCDOT "could have utilized" for staging. By lending a parcel it owns, rent-free, the Town gets written terms on where construction trucks come and go. It also keeps trailers away from the island's most visible frontage and off the multipurpose fields that host so much of its public life. The rent the Town gives up buys it a voice in how the site is run.

The Garden at the Southern End Stays Open

The memo sets aside one carve-out by name: "A portion of the southern end of the property will remain open and accessible to the public for purposes of accessing the Harbor Way Garden."

That protection carries weight because of the garden's history. According to the Harbor Island Garden Club, Harbor Way Gardens began in summer 2003, after club members proposed turning town property into a public garden. The Town's Parks and Recreation and Public Works staff cleared the site and laid out paths. Since 2006, the club's brick-and-paver fundraising has helped pay for maintenance and future projects. The garden now has entry arbors, a recirculating fountain and three other water features, garden sections with labeled plants, a Witherspoon Rose Culture area, and little libraries. A construction yard next door will change the sound and traffic around the garden. Under the drafted terms, it does not cut off access.

The drafted terms also keep the existing drainage swale along the northern boundary of the property "in place and unobstructed."

The Market Has Already Moved On

Monday shoppers are already used to the field sitting empty. For the 2026 season, Port City Daily reported that the Wrightsville Beach Farmers Market moved to the Wrightsville Beach Park Softball Field. It runs every Monday from 8 a.m. to 1 p.m. through December 7, with free parking next to Causeway Drive. The Town's market rules place it on municipal grounds at 321 Causeway Drive, between Seawater Lane and Salisbury Street.

Counting from the first Monday in November, the market has six Mondays left this season, ending with the December 7 date. Its new location is a short walk from the field that is expected to become the bridge yard.

When the Yard Starts to Matter

The draft MOU sets no calendar start date for the trailers. The project around it is already moving, though, and these are the published milestones:

  1. Contract awarded. WECT reported on October 1 that NCDOT awarded Balfour Beatty an $8.67 million contract for Phase 1. That phase covers waterline relocation and the smaller bridge on West Salisbury Street over Lees Cut.
  2. Waterline work this fall. Crews were set to begin in October. WECT put the work at four to six weeks, and Port City Daily put it at four to eight. Both reported that equipment would sit on Pelican Drive and the shoulder of West Salisbury Street, with no expected traffic impact.
  3. Lees Cut closure. After the waterline work, West Salisbury Street over Lees Cut closes to traffic so crews can build the replacement. An official closure date has not been announced.
  4. The larger bridges. Port City Daily reported that construction on the Salisbury Long Bridge is expected in summer 2027, followed by the Causeway bridge. It put the full replacement cost at $105 million.
  5. The finish line. The StarNews reported in August that NCDOT was targeting completion by spring 2030. NCDOT's project page, last updated September 3, 2026, lists completion as 2030 to 2032.

Add the 60-day restoration window to either end date, and the field's return to Town use falls somewhere in the early 2030s.

The Same Agenda, the Same Approach

The field agreement was not the only item on the October 14 agenda about how the bridge years will look on the ground. In each case the Town was putting its own resources into a state project.

On bridge appearance, a staff memo says the Board had already preliminarily approved a decorative two-bar metal rail at $153,112.50, along with decorative lighting through a separate agreement with Duke Energy. A decision on staining or coating was deferred, and Town-logo medallions were still undecided. The draft agreement with NCDOT has the Town paying for these additions, handling their maintenance, and being invoiced when the project is complete.

On the Loop, the consent agenda included Budget Ordinance (2026) 696-B. It would accept and appropriate a $1,500,000 award from the New Hanover Community Endowment for improvements to the John T. Nesbitt Loop. It would also rename the existing License Plate Fund as the Loop Improvement Fund. In March, WWAY reported that the Town was looking at design, lighting and pedestrian safety on the 2.45-mile loop, and at "mini loops" or other walking routes for when the bridges close.

Taken together with the Sea Water Lane agreement, the pattern is consistent. NCDOT is building the bridges and paying for them through its improvement program. Meanwhile, the Town is deciding with its own land and money where the trucks will park, what the railings will look like, and where people will walk while it all happens. A rent-free field with a guaranteed path to the garden is the clearest example of that.

Questions about how the bridge years might affect a particular street, a planned renovation or the timing of a sale are worth a conversation that starts with a specific address. Lynne Galloway has lived on Wrightsville Beach since 1999 and is glad to talk through what the construction schedule could mean for your property. Let's Connect.

Let's Get Started

I am committed to guiding you every step of the way—whether you're buying a home, selling a property, or securing a mortgage. Whatever your needs, I've got you covered.

Follow Me on Instagram